The end of a date range has to stay on or after the start. Save will not send a range that runs backwards.

A date range that runs backwards stays on the screen and is explained under the end. Save does not send it.

The three sentences ​

The explanation sits under the end field, in an alert. A missing start or a missing end is left open: one date on its own is allowed.

What is wrongWhat the alert says
The end is before the start{end} must not be before {start}.
The end is the same moment as the start, on a pair that requires the end to be later{end} must be after {start}.
A date and time cannot be readChoose valid dates and times for {start} and {end}.

{start} and {end} are the names of the two fields. When the screen does not pass its own names, those words are Start and End.

The values you typed stay in the boxes. Fix the end, or clear it.

A pair of times with no dates, such as Daily sending hours, is not this check. 22:00 followed by 02:00 is a valid overnight window.

On a date-and-time pair, a repeated hour when the clocks change can look earlier on the clock while the two moments are still in order. That pair does not raise the alert.

A half-typed date is a different hold. Save then says “Finish or clear the date in {field} before saving.” That sentence is about an unfinished box, not about the order of the two dates.

On a campaign ​

Open the campaign, then Main, then Advanced Settings.

  1. Activity period start and Activity period end are inclusive dates in the brand time zone. If the end is before the start, the alert under Activity period end reads “Activity period end must not be before Activity period start.”
  2. Stop date (UTC) has to fall after the start it is checked against. With the activity period on, that start is Activity period start. On a Broadcast set to Once, on a date, the start is that scheduled date and time. The same moment is refused. The alert names Stop date (UTC) and the start field, and says the stop date must be after that start, or must not be before it when the stop date is earlier.
  3. Press Save. The range is refused before the save is sent. The dates stay where you left them.

Disable and Archive can still be saved when the only change is that status. A stored range that already runs backwards does not block those two.

Where the same rule appears ​

These screens use the shared check. The alert still says Start and End, because these screens do not pass their own field names into it.

ScreenWhat you see beside the datesWhat the alert calls them
A customer, Timeline, Events, and CommunicationsFrom:, To:Start, End
Activity FeedFrom:, To:Start, End
Ingest monitorFrom:, To:Start, End
A report under ReportsFrom, ToStart, End
Home, on a custom periodNo printed label. The boxes are named From and To for assistive tech.Start, End
Data Studio, Period set to Custom datesNo printed label. The boxes are named From date and To date for assistive tech.Start, End

The same calendar day in the two boxes is allowed on these filters. The alert appears when the end day is before the start day.

Audit uses the same order check and prints its own sentence: “End date must be on or after start date.” The fields are From (UTC) and To (UTC).

Winners uses the same order check and prints “The start date is after the end date.”

Other save forms share the check. Their field labels are not listed here. The sentences above are the ones those forms use when they use the shared alert.